This is our Journey for Industrial Plant Project Experiences

PROJECT

CLIENT / MAIN CONTRACTOR

PERIOD

LOCATION

WORK SCOPE

Sakura Shoe Manufacturing Plant Project SJI (PT.KMK) CKI (PT. Cakra Kencana Indah) Jun 2019 – Jul 2020 Temanggung, Central Java Steel Structure Shop Fabrication & Field Erection Work
SRI-U3 (AY3201 Steel Structure Work Combined Package 1&2) PT Synthetic Ruber Indonesia (SRI) PT Karya Persada Tehnik  (IKPT) Aug 2016 – Sep 2017 Ciwandan, Cilegon Steel Structure Site Installation Work
Piping Work of Banggai Ammonia Plant PT Panca Amara Utama PT REKAYASA Jan 2016 – Jul 2017 Luwuk, Central Sulawesi Piping Field Installation Work
Ngoro Beverage Aseptic Plant Project PT Hon Chuan Indonesia Mar 2014 – Mar 2015 Mojokerto, East Java Indutrial Plant EPC Work
Indonesia Grinding Mill Plant Project (ADIK) Molycop Group PT Comsteel Indonesia Feb 2012 – Jan 2014 Cilegon, Banten EPC
Daekyung Plant Project – Office Building & Shop PT Daekyung Industry Apr 2009 – Feb 2010 Cilegon, Banten EPC
Intake & Demin Area Piping, Tank & Civil Work PT. Kirin Miwon Foods Feb 2007 – Jul 2007 Lampung, Sumatra Civil & Piping
Clean Water Project Installation & Piping PT. Primer Koperasi Angkatan Darat Jul 2005 – Mar 2006 Bandung Civil, M&E
Drainage Pipe Fabrication & Erection Yamaha Indonesia May 2005 – Jun 2006 Cikarang Civil
Fabrication STL/ STR PT. Cilegon Fabricator Jan 2005 – Mar 2005 Cilegon, Banten M&E
Fabrication Work Chimney PT. Mandiri Maju Jaya Oct 2003 – Nov 2003 Jawa Civil
Mechanical & Piping Work PT. Punj Llyod Jan 2003 – Nov 2003 Sumatra Steeel Structure, Piping & Mechanical
RTGC, RMQC, Erection, SAGT, RTGC 2 & Fabrication Hanjung Enginering & Construction CO, LTD Aug 2000 – Sep 2003 Lampung, Sumatra M&E
Dongwoo Project PT. Daewoo Corporation Aug 2002 – Mar 2003 Cikarang, Bekasi Mechanical
Piping Work for T-Project Engineering & Piping Work Refinery & Fermantation PT. Kolon Engineering Jan 1997 – Sep 1998 Pasuruan Building, M&E
UA #3 Project EQ Erection & Piping Temporay Office Work Platform & Ladder PT. Shinwa E & C May 1997 – Feb 1998 Merak, Banten Civil, M&E
Piping Work PT. KIA Timor Motor Oct 1997 – Sep 1998 Jombang M&E
Installation of Gantry & Door Line PT. Chell Samsung Sep 1997 – Nov 1997 Cikampek, Jawa Civil, M&E
EQ Erection, Insulation, Piping, Additional Work, Fabrication of Operation Goods PT. Chell Samsung Sep 1996 – Apr 1997 Serang, Banten Civil & Building
ISP-5 Project: Silo, Fabrication, Erection, SSP, CP, OSBL, SSP & OSBL, TPA Work, ISP-V PT. Sunkyong Keris Feb 1996 – Dec 1996 Tangerang, Banten Civil, M&E, Insultation, Conveying, Additional Work
ISP-4 Project: Duct Work, IBL Piping, Add Work PT. Sunkyong Keris May 1995 – Jun 1996 Tangerang, Banten M&E
Carrier & Dryer PT. Sunkyong Keris Nov 1994 – Jan 1995 Cikarang, Bekasi Building, Civil. ME
Extractor Carrier Print Cover Work PT. Yassam Textile Co Nov 1994 – Jan 1995 Cikarang, Bekasi Civil and Building
ISP-3 Project: Jacket & Single Piping, EQ Erection, Tank, TPA, Insulation & Painting PT. Dae Hwa Leather Jan 1994 – Sep 1994 Tangerang, Banten Manufacturing Shop, Storage, M&E Work
ISP-2 Project: QS Duct, General Duct, T/UP Foundation Rail, S/B, G/P, Pre-Fabrication Tank PT. Lucky May 1993 – Sep 1993 Tangerang, Banten Mechanical
ISP-1 Project: QS Duct, Support Frame, General Duct, Kolene Facility, Take-up Frame PT. Sunkyong Keris Oct 1991 – Sep 1992 Tangerang, Banten Building, Civil. & Mechanical